.

Architectural, Engineering & Construction Defect Litigation

The Architectural, Engineering and Construction Defect Litigation Practice Group of Marshall Dennehey clearly understands the relationship between construction professionals and their respective responsibilities. Our practice group has a considerable number of years of experience in defending construction industry cases. The practice includes representation of owners, developers, general contractors, construction managers, subcontractors and design professionals. This group quickly develops an understanding of the project and contract documents in order to identify key issues early, then proceeds to develop those issues into sound defense strategies. Our practice group's litigation experience includes initial negotiations, construction claims, arbitration proceedings and jury trials involving all phases of construction litigation.
 
Our defense approach is aimed at the early identification of key issues and is predicated on developing the earliest possible defense strategies tailored to the individual case and client. The application of this strategy is carried out by a team approach consisting of experienced partners, associates and paralegals capable of handling the basic, as well as the highly sophisticated and complex, construction litigation matters.
 
The Architectural, Engineering and Construction Defect Litigation Practice Group of Marshall Dennehey consists of a diverse group of professionals with considerable experience handling matters throughout Pennsylvania, New Jersey, Delaware, Ohio, West Virginia, Florida, New York and Connecticut. The group prides itself on its multi-jurisdictional range of experience and substantial number of cases handled.
 
We look forward to your inquiries and remain at your disposal for presentations or seminars which your company may desire.

Results

Multimillion Dollar Default Judgment Successfully Struck Down by Appellate Court

We succeeded in striking a $4.1 million default judgment entered in the Philadelphia Court of Common Pleas by a plaintiff who alleged defective residential construction. We convinced the court that Pennsylvania Prothonotaries and Clerks of Court lack authority to accept a praecipe to enter a default judgment in a specified amount unless the amount is approved by a judge or is a sum certain, meaning that the amount is ascertainable from a confessed judgment or a contract that specifies the amount due. The default judgment had spawned significant coverage litigation by and against the defendant’s insurer.

Summary Judgment Secured in a Design Defect Case

We won summary judgment on behalf of a company that provided software for the overall design of roof trusses in a design defect case. The plaintiff owned the apartment complex being built and hired Turnbull Wahlert to construct the building. 84 Lumber was subcontracted by Turnbull to build and install the roof trusses. 84 Lumber contracted with our client to use its software for the design of the roof trusses and to provide truss connect plate hangers. The building experienced severe water damage allegedly because the roof trusses were not sloped properly and the HVAC units were misplaced on the roof. Damages were estimated at over $1.2 million. 84 Lumber demanded that our client defend and indemnify it against Turnbull’s allegations. The court granted our motion for summary judgment.

Thought Leadership

Case Law Alerts

Closing the Loophole

July 21, 2026

On November 17, 2023, New York amended the Prompt Payment Act, establishing a 5% cap on retainage under section 765-c of the General Business Law. Specifically, this amendment limited any retainage withheld from a contractor or subcontractor on a private construction project to 5%.  However, this amendment contained a significant gap: because the 5% limitation was not included among the void provisions enumerated in Section 757 of the General Business Law, owners and general contractors were able to circumvent the statutory cap through contractual provisions requiring higher retainage. Section 756-a of the General Business Law allowed the terms of a construction contract to supersede the Prompt Payment Act "except as otherwise provided" in the article. SB 5655, which went into immediate effect on December 19, 2025, closes this loophole by adding contract provisions that exceed 5% to be void and unenforceable under Section 757 of the General Business Law. 

Case Law Alerts

Contractor Prevails on Contractual Risk of Loss Provision

July 21, 2026

Carnaval Home hired Berman Construction to renovate an existing home owned by Carnaval. Their contract set the date of substantial completion at September 4, 2019, and included a risk of loss provision placing risk predominantly on Carnaval. Berman hired subcontractors, including an electrician and project supervisor, to carry out the renovations. On July 29, 2019, with renovation 90% complete, a fire destroyed the home. Carnaval then sued Berman for breach of contract, negligence, and violation of Florida building code. Carnaval based its breach of contract theory primarily on Berman failing to deliver the renovated property by substantial completion. At trial, Carnaval presented evidence that faulty attic wiring caused the fire, while Berman claimed it was caused by arson or another cause beyond its control. During the charge conference, Berman requested a question on the verdict form regarding the risk of loss provision and its other defenses of impossibility of performance and frustration of purpose. The trial court granted a directed verdict on impossibility of performance and frustration of purpose, holding the risk of loss provision eliminated those defenses, and also denied Berman’s request for the risk of loss question on the verdict form. The verdict form ultimately included questions regarding the breach, negligence, and code violation claims. Its questions regarding the breach claim included the following: whether Carnaval did what was required by contract; whether Carnaval was excused from doing what was required by contract; whether Berman failed to do what was required by contract; and whether Carnaval was damaged by Berman’s failure to perform. The jury found Berman was not negligent but did violate the building code and breach its contract, though the code violation did not cause Carnaval’s damages. Carnaval was awarded $928,850 pursuant to the breach claim. The trial court denied Berman’s post-trial motions and granted Carnaval’s motion for attorneys fees. On appeal, the 4th DCA noted that Carnaval presented evidence that the fire occurred the day electrical work was completed and power was restored to the house for the first time since construction began, when the home was under the exclusive control of Berman and its subcontractors. It presented testimony from the carpenter that the kitchen and family room lights went out while he was at the property that evening, which was also corroborated by Carnaval principal Luis Ormo. It presented expert testimony that the fire likely started in the attic and was not a result of arson. Berman offered testimony that traces of gas were detected along with unusual burn patterns and heat deformation at the bottom of door frames. Its expert testified that the fire had multiple points of origin. Berman established the home was engulfed in flames emanating from the roof within twenty minutes of Carnaval leaving the property and argued the fire could not have moved so fast absent arson. It further suggested the electrician and Ormo had separate dealings in violation of their subcontract, thus some of the electrician’s conduct was beyond Berman’s control. The 4th DCA held Berman’s claim of inconsistency between the negligence, building code violation, and breach jury verdicts was to be remedied by a new trial, not directed verdict, and further held that it did not have to decide whether the verdict was truly inconsistent as Berman did not raise this issue before the jury was discharged and did not seek the appropriate remedy of a new trial. As such, it held the trial court was correct in denying Berman’s motion for directed verdict. However, the court held that the trial court erred in denying Berman’s special interrogatory request as to the risk of loss provision. It explained that, where interrogatory verdict forms are used, it should include questions on both the plaintiff’s claims and any affirmative defenses. Without allowing a question regarding whether the risk of loss provision excused Berman from performance, the trial court did not resolve “the major question in the case.” The jury, having found Berman not negligent, made Berman’s defense, and the verdict form question, particularly significant. The court rejected Carnaval’s argument that Berman had waived its demand for arson-specific instructions and that Berman bore the risk of loss from non-arson-induced fires. It also held that Carnaval incorrectly applied the negative-implication canon, wherein the express mention of one thing implies the exclusion of another, stating not every positive statement of rights or obligations carries a negative implication. Further, the risk of loss provision’s clause including “perils beyond contractor’s reasonable control” amounted to a catch-all, to which the negative-implication canon cannot be applied. When read in totality, the provision clearly places risk of loss on Carnaval for perils such as arson. Berman was therefore entitled to have the jury decide whether the loss was caused by arson or another peril beyond its control. Final judgment in favor of Carnaval was reversed, as was the trial court’s order denying Berman’s motion for attorneys fees, and the matter was remanded for a new trial.

Firm Highlights

Thought Leadership

United State District Court for the Middle District of Florida finds Evidence of Replacement Cost Value is Admissible and Recoverable Even When Repairs Have Not Been Made

The plaintiff filed a claim for damage as a result of Hurricane Ian. It claimed damages were over $24 million, but the carrier accepted partial coverage and paid $8,307.49 for secondary components. The carrier found hurricane damage to the building, but it was below the insurance policy’s $3.6 million deductible. The plaintiff sued for breach of the insurance policy. The carrier argued in a motion for summary judgment that plaintiff could not recover replacement cost value (RCV) because the property repairs had not been effectuated. The policy provided for RCV, but only after the repairs were completed. The carrier argued that because the repairs were not completed, the plaintiff was not entitled to RCV damages. The plaintiff argued the carrier could not withhold the actual cost value (ACV) due, which was the main allegation of the lawsuit, then fault it for not making the repairs to unlock the RCV. The United States District Court for the Middle District of Florida rejected the carrier’s argument, finding that when an insurer allegedly breached the policy by withholding coverage, it could not hide behind a repair-contingent provision to block the insured from RCV damages at trial. The court found the issue to be whether the contractual language designed to preclude certain coverage until after repairs are completed barred an insured from seeking those damages at trial when repairs were not complete. The court noted the Eleventh Circuit had not resolved this issue and neither side pointed to a definitive answer from the Florida Supreme Court. The court reasoned that it must look to the Sixth District Court of Appeal (6th DCA), which is the court which would have heard this case if it was in state court. The court noted the 6th DCA recently addressed this issue in Universal Prop. & Cas. Ins. Co. v. Rodriguez, 427 So. 3d 676 (Fla. 6th DCA 2026). The Rodriguez Court found that a breach of contract action is designed to adjudicate not only whether the contract was breached, but also evaluate the damages incurred had the breach not occurred, which the Rodriguez court found to be recovery of the RCV. This court also noted basic Florida contract principles compelled the same result, as a material breach frees the nonbreaching party to suspend its own performance and can demand the full benefit of its bargain, including RCV damages. Finally, the court found the distinction between a full denial and partial denial did not compel a different result. It found the policy required the carrier to acknowledge coverage and pay ACV for all covered damages, and the failure to do that is a material breach, entitling the insured to all of the damages available under the contract, which included the RCV.

Thought Leadership

Appeals Court Reverses Trial Court Order Awarding Attorney’s Fees Due to Lack of Evidence to Support Fee Awarded

The Fourth District Court of Appeal reversed the trial court’s order awarding appellate fees to People’s Trust Insurance Company based upon a lack of evidence to support the attorney’s fee award in RM & Assocs. Consulting, Inc. v. People's Trust Ins. Co., 2026 Fla. App. LEXIS 4654 (Fla. 4th DCA 2026). People’s Trust was the insurer of a residential property that had sustained water damage. RM & Associates Consulting was hired by the homeowner to perform mitigation services at the property. The homeowner assigned post-loss benefits to RM and RM subsequently filed suit against People’s Trust alleging that it had not been paid the money it was owed for the mitigation services. People’s Trust defended the lawsuit on the ground that the policy required the insured to notify the insurer before authorizing repairs so People's Trust could elect to use its preferred contractor. Because the owner did not comply with that provision, People's Trust asserted its liability was limited to the amount that its preferred contractor would have charged for the work, which People's Trust contended was $2,000. People's Trust paid that amount to RM before RM filed suit. People’s Trust filed a motion for summary judgment which was granted. RM appealed the summary judgment ruling and the ruling was upheld by the Fourth District Court of Appeal. The appellate court also granted People’s Trust’s entitlement to appellate attorney’s fees, subject to the trial court’s determination of the amount of fees, based upon an offer of judgment made by People's Trust. On remand, the trial court held an evidentiary hearing to determine the amount of attorney’s fees People’s Trust was entitled to. At the hearing, People’s Trust presented testimony from it’s fee expert, supervising trial counsel and appellate counsel. People’s Trust sought recovery of $24,866.17 for work performed by appellate counsel. The request primarily consisted of work performed in preparation of the answer brief. The fee expert testified that more than ninety hours spent preparing the answer brief was reasonable given the complexity and significance of the underlying issue. The appellate court found that the fee expert’s testimony fell short of meeting the necessary standard of demonstrating that the hours expended were necessary. The appellate court found that the billing records did not serve to cure the deficient testimony, as the billing records did not contain adequate details regarding the specific tasks performed. Rather the records contained entries such as “answer brief” which the appellate court found to be insufficient. The appellate court noted that neither the fee expert or counsel addressed how the prior research and briefing in the parallel litigation informed the work in the instant matter. The appellate court noted this was significant in that a court's attorney's fees award must exclude excessive, redundant, or otherwise unnecessary hours, citing Florida Patient's Compensation Fund v. Rowe, 472 So. 2d 1145 (Fla. 1985). Based upon the record failing to support the finding of the trial court, the 4th DCA remanded the case to the trial court for a reconsideration and redetermination of reasonable appellate attorney’s fees supported by competent substantial evidence. The 4th DCA reiterated that the fee expert’s focus on the quality of the work and the importance of the work to People’s Trust did not make up for the perceived deficiencies in the position that spending over ninety hours on a single answer brief was reasonable. Whether moving for attorney’s fees or challenging the amount of fees being sought by an opposing party, practitioners should be mindful of the evidence being used to support the claims being made. Parties should pay close attention to whether the hours being sought may be impacted by prior litigation either party may have engaged in. A party must be prepared to address how prior litigation efforts did or did not impact the amount of hours being claimed in current litigation. Lastly, billing records must be sufficiently detailed so as to support any potential future fee claim.

Thought Leadership

First DCA Reverses Excessive Jury Award Unsupported by the Evidence

In December 2019, the plaintiffs filed a claim with Universal for damages caused by a water and sewage back up through the plumbing system and existing through multiple fixtures including the washing machine drain, kitchen sink, dishwasher, bathtub and toilet. Universal investigated the claim, issued payment for resulting water damage totaling $7,000.00 in actual cash value ($12,000.00 in replacement cost value). The plaintiffs sought additional benefits for work needed to access the below-slab cast iron plumbing system due to the failure of the system from rust, deterioration, corrosion and breaks in the line. Universal denied any additional benefits for access. In 2021, the plaintiffs filed suit. During litigation, Universal sent a plumber to inspect the home and the plumber concluded the pipes were clogged but could be cleaned. The plaintiffs’ plumber testified that the plumbing system needed to be replaced due to holes and openings in the pipes. The plaintiffs introduced two estimates prepared by Triad Restoration services totaling $79,680.22 in replacement cost value and $50,219.97 in actual cash value and an executed contract with another company for repairs with the amounts of repair redacted. Since the insurance policy did not provide coverage for repair or replacement of the plumbing system, the jury only had to decide whether the plumbing system needed to be replaced, and if it did, Universal would owe for the access costs; the jury verdict form required the jury to determine both the replacement cost value and actual cash value amounts. The jury asked if it had to rely on the Triad estimates for their amounts. The trial court advised the amount awarded had to be based on the evidence presented at trial and the law given by the trial court. The jury awarded $335,000.00 in replacement cost value or $305,000.00 in actual cash value. Universal motioned for a new trial arguing the amount awarded was unsupported by the evidence and then moved for remittitur. The trial court denied both motions and this appeal followed. The court found that while a jury’s verdict should only be disturbed with caution and discretion, the trial court must give the properly challenged award close scrutiny and determine whether it bears a reasonable relation to the damaged provided, is supported by the evidence, and could have been reached in a logical manner by reasonable means §768.74(3), (5)(d)-(e), Fla. Stat. The court found the trial court did consider the statutory requirements at the hearing on Universal’s remittitur motion and was concerned about a reasonable relation to the amount of damages proved and injury suffered and whether the award was supported by the evidence, but ultimately denied the motion, reasoning that the jury had been properly instructed to fairly and adequately compensate the plaintiffs. The court noted the only evidence providing the basis for the jury verdict was Triad’s estimates and those valued the plaintiffs' claimed loss at $79,680.22 in replacement cost value and $50,219.97 in actual cash value; no valuation evidence reasonably supported the jury verdict. The plaintiffs argued that the jury was entitled to consider more than the estimates, but the court conveyed the evidence provided did not give the jury a way to reach the amounts they awarded. The court was also not swayed by the plaintiffs’ argument regarding inflation and later price increases, but the court noted that no evidence via the contract, nor testimony regarding increase in labor, material, fuel or construction costs were entered into the record.  The court concluded the jury may draw reasonable inferences from the evidence, but it may not supply a damages number by speculation. The court did not find any of the plaintiffs’ remaining argument persuasive either. The court reversed the denial of Universal’s remittitur motion and motion for new trial as to damaged and remanded the case. The court ended its opinion with advising the trial court must determine whether replacement cost value or actual cash value is the property measure of damages under the policy and order remittitur in an amount consistent with that determination and the evidence.