.

Results

  • Multimillion Dollar Default Judgment Successfully Struck Down by Appellate Court

    We succeeded in striking a $4.1 million default judgment entered in the Philadelphia Court of Common Pleas by a plaintiff who alleged defective residential construction. We convinced the court that Pennsylvania Prothonotaries and Clerks of Court lack authority to accept a praecipe to enter a default judgment in a specified amount unless the amount is approved by a judge or is a sum certain, meaning that the amount is ascertainable from a confessed judgment or a contract that specifies the amount due. The default judgment had spawned significant coverage litigation by and against the defendant’s insurer.

  • Summary Judgment Secured in a Design Defect Case

    We won summary judgment on behalf of a company that provided software for the overall design of roof trusses in a design defect case. The plaintiff owned the apartment complex being built and hired Turnbull Wahlert to construct the building. 84 Lumber was subcontracted by Turnbull to build and install the roof trusses. 84 Lumber contracted with our client to use its software for the design of the roof trusses and to provide truss connect plate hangers. The building experienced severe water damage allegedly because the roof trusses were not sloped properly and the HVAC units were misplaced on the roof. Damages were estimated at over $1.2 million. 84 Lumber demanded that our client defend and indemnify it against Turnbull’s allegations. The court granted our motion for summary judgment.

  • Successfully Defended Architect in Construction Defect Matter

    We successfully defended an architect against a $7 million claim brought by a general contractor in connection with the renovation of a historic, city-block-sized building in Philadelphia. The contractor alleged design errors and sought additional damages under the Contractor and Subcontractor Payment Act, inflating its claim to $16 million. During contentious discovery, we exposed contradictions and falsehoods in the contractor’s testimony, leading to a partial summary judgment that dismissed the bulk of claims against our client. Facing a looming trial and a remaining $4 million claim, we worked with the building owner’s counsel to convince the settlement judge of the claims’ lack of merit. The plaintiff filed for bankruptcy, and the final settlement had to be approved in the Bankruptcy Court. The case settled for just $362,500, with our client paying only $181,250—an outstanding result in a high-stakes dispute.

  • Florida Court Affirms Arbitrator’s Decision in Construction Defect Case

    We successfully upheld an arbitrator’s ruling in a $13 million construction defect case, defeating claims that our client negligently recommended windows and doors for a coastal Florida home. The owners’ direct claims against the general contractor and our client, the window and door supplier and installer, were arbitrated. The owners claimed the window company misrepresented the fitness of the windows and doors for use in Florida’s coastal environment. We argued that the windows and doors were specified by the owner and architect and that our client performed proper due diligence by visiting the manufacturing facility and consulting with the manufacturer’s engineers with regard to the application. The arbitrator found no liability as to our client because there was no evidence it was negligent in its recommendation of the product.

  • Dismissal of Breach of Contract and Professional Malpractice Claims Achieved at Trial

    We achieved dismissal of a breach of contract and professional malpractice claim against a professional engineering firm that provided construction monitoring services for a lender. When the project went south (for a multitude of reasons unrelated to the engineer's services), the project developer, who had obtained an assignment of rights from the lender, sought to hold the engineer responsible for project cost overruns. After a seven-day bench trial and testimony from nine witnesses, the court dismissed the complaint in its entirety. In dismissing the breach of contract claim, the court held that the plaintiff failed to establish any breach of contract by the engineer, finding that the reports prepared by the engineer during the course of the project complied with its contractual obligations, with the terms of the contract being clear and unambiguous. This included a contract provision which stated that the engineer was not responsible for the malfeasance of others, including the general contractor, or the errors and/or omissions of the project architect. The court further found that, even had the plaintiff proven that there was a breach of contract by the engineer, the plaintiff still failed to prove that the lender sustained any actual damages. In dismissing the professional malpractice cause of action, the court found that the expert testimony by the plaintiff was insufficient to establish a prima facie case. Specifically, the trial testimony on the plaintiff's direct case failed to establish any deviation from the accepted standards of practice in the services the engineer provided as the lender's representative.

  • Favorable Precedential Decision Obtained in High-Stakes Construction Defect Case

    We prevailed in a unanimous, precedential decision in the Superior Court of Pennsylvania, which reconciled conflicting case law in the state. The plaintiffs were joined by 55 amici, and our client was joined by numerous construction organizations as amici. The court eventually applied Pennsylvania’s statute of repose to bar construction defect claims brought by homeowners.

  • Summary Judgment Secured Against Leading Construction Defect Law Firm

    We obtained a summary judgment on behalf of our architectural client against one of the top construction/design defect law firms in New Jersey. After three separate argument appearances, the court granted summary judgment, holding that the plaintiff’s expert’s report failed to substantively establish a deviation from the architectural standard of care.

  • Summary Judgment Granted in Highly Contested Construction Defect Case

    We were granted summary judgment in a $1.3 million construction defect subrogation case involving allegedly improperly sealed roof openings. The subcontractor contested its liability on the theory that our client chose the sealing method, and that the contract itself was deficient. Our motion, that was eventually granted, successfully argued that the contract language met the standard set in Pennsylvania’s Perry-Ruzzi rule.

  • Defense Prevails in Construction Defect Case

    We obtained summary judgment on a construction defect claim in Susquehanna County, Pennsylvania. The court dismissed the plaintiffs’ claims against the defendant, a homebuilder, in their entirety for the plaintiffs’ failure to adequately prove breach of contract, breach of express and implied warranties, fraud in the inducement, wrongful conversion and various alleged violations of the Pennsylvania Unfair Trade Practices Act.

  • Turf War - Summary Judgment for Synthetic Turf Field Installer

    We obtained summary judgment in the Philadelphia, PA Court of Common Pleas in a case involving the alleged defective design and installation of a synthetic turf field. Our client was the alleged installer of a turf field located at a popular venue for recreational athletics. The plaintiff sustained a full tear of his right ACL, a complex tear of the medial meniscus and partial tear of the IT band when he tripped on an exposed seam in the turf. Discovery revealed that a flood occurred during turf installation, arguably impacting the outcome. Nevertheless, the court granted our motion for summary judgment premised on an argument that the plaintiff could not establish a deviation from the standard of care for turf installation in the absence of qualified expert testimony.

  • Appellate Victory on Behalf of Mall Owner

    The appeal was brought before the Appellate Division, Second Department. The plaintiff was a pedestrian who was struck by a car in the mall parking lot and sued our client, the mall owner. The plaintiff claimed that the parking lot was negligently designed, which led to the accident. The trial court granted summary judgment to the mall, saying that there was no evidence that the parking lot was negligently designed, or that the design led to the accident. A unanimous appellate court affirmed.

  • Arbitration Defense Verdict for Prominent Florida Real Estate Developer

    Marshall Dennehey and its shareholder, Jonathan E. Kanov, Esq., were successful in a South Florida arbitration representing a prominent Florida real estate developer against construction damage claims brought by a neighboring property’s condominium association. In a final, binding ruling, the arbitrator issued a complete defense verdict, plus an award of attorney’s fees and costs to the developer. The plaintiff condominium association had contended that construction of the developer’s luxury condominium tower caused many areas of their property to be damaged, largely from vibrations/seismic activity during demolition and construction. The plaintiff demanded $1.2 million in damages pursuant to a contract that was entered into by the parties covering the construction activity.   The arbitrator agreed with the defense’s arguments that the “conditions the claimant contends were caused by vibration damage from construction activities are actually age-related deterioration and the result of deferred maintenance. Additionally, there is no evidentiary basis to allocate uncompensated damage associated with the pool and pool deck to the developer, as opposed to preexisting conditions requiring repair and upgrades required for code compliance.” Marshall Dennehey presented highly credible experts and fact witnesses in support of its defense.    Another key to the defense verdict was Marshall Dennehey’s effective cross examination of the claimant’s structural engineering expert on construction vibration/seismic activity data, which formed the crux of their damage claims.

  • Defense Prevails in Multi-Party Construction Defect Action

    The decision was later affirmed by the Superior Court of New Jersey, Appellate Division, and we successfully argued both the summary judgment motion and the appeal. The plaintiff, a condominium association, filed suit against the sponsor of a newly constructed mixed-use residential and commercial building in Hoboken, New Jersey. The plaintiff also sued the property management company, the general contractor and various subcontractors involved in the construction. A temporary certificate of occupancy was issued in March 2004 and the plaintiff did not commence litigation until June 2014—more than ten years after substantial completion. Therefore, the claims were barred by the ten-year Statute of Repose, N.J.S.A. § 2A14-1.1. The former property manager for the building and the sponsor entity had common ownership. The plaintiff argued the sponsor maintained control of the property by virtue of its continued involvement through the property management entity, and that the Statute of Repose did not apply to a party in actual possession and control of the property at the time that the defective and unsafe condition caused the injury or damage at issue. The Appellate Division held that the plain language of the Statute of Repose precludes any “action, whether in contract, in tort, or otherwise, to recover damages for any deficiency in the design, planning, surveying, supervision or construction of an improvement to real property, [and] any action for contribution or indemnity for damages sustained on account of such injury . . . more than [ten] years after the performance or furnishing of such services and construction.” N.J.S.A. 2A14-1.1(a). The court found that the claims were also barred by the six-year statute of limitations as the plaintiff alleged that the first repairs at the building were undertaken in 2004, and the complaint was not filed until 2014.

  • Summary Judgment for Plumbing Contractor in Construction Defect Case

    We obtained dismissal of the plaintiff’s complaint and all cross claims against our client, a commercial plumbing contractor, on a motion for summary judgment in a construction defect case. ​The case involved claims by a homeowners association for property damage and replacement costs allegedly in excess of $6 million as a result of construction defects in the design and installation of plumbing, water collection, drainage, grading, and other water runoff and drainage systems. In addition to our client, the named defendants were the project architects, the general contractor, various plumbing, electric, concrete and grading trades, and the water and electric utilities, all of whom asserted cross claims. We were granted summary judgment on grounds that the plaintiff’s breach of contract claim failed due to lack of privity and proof that the plaintiff was not a third-party beneficiary of our subcontract. All claims and cross claims for negligent installation/breach of warranty were dismissed upon proof that our client’s work was performed in accord with project specs and in accord with the applicable building code, and that none of its work contributed to any drainage issues or resulting property damage.

Firm Highlights

Thought Leadership

Employer Not Entitled to Increase Social Security Retirement Benefit Offset Based on Social Security Cost of Living Adjustments

This case involved a claimant who sustained a work injury in 1997, which the employer accepted. The claimant began receiving Social Security Retirement (SSR) benefits in March 2017, and the employer began reducing those benefits under Section 204(a) of the Act. The claimant subsequently received Cost of Living Adjustments (COLA) to her SSR Benefits, and each time, the employer increased its offset, without challenge by the claimant, until 2023, when the claimant filed a Petition to Review Benefit Offset. The WCJ granted the petition, concluding that the offset in Section 204(a) is set at the time the SSR benefit is received, and should not be readjusted based on SSR COLA increases. The employer appealed, and the Board reversed, interpreting Section 204(a) to unambiguously allowing the offset of 50% of all SSR benefits. According to the Board, they could not read into the offset language of the Act an exception for COLA increases to Social Security offsets, where no such language existed. The claimant appealed to the Commonwealth Court, and the Court reversed the Board. In doing so, the Court held that the Board’s interpretation of Section 204(a), permitting the employer to increase its offset based on the claimant’s receipt of a COLA increase to her SSR benefits, was contrary to the intent of the General Assembly, the intent of the United States Congress and the humanitarian purpose of the Act. The Court pointed out that the purpose of the 1996 amendment to the Act relative to offsets for SSR benefits was to provide reasonable cost containment for employers and should not be used to allow employers to obtain a windfall by receiving credit for amounts not intended by the General Assembly.

Thought Leadership

WCJ Cannot Apportion an Award of Benefits for Vision Loss Based on the Percentage of Vision Loss that Existed Before the Work Injury

In this case, the claimant filed a Claim Petition alleging that he suffered a work injury to his right eye. The Workers’ Compensation Judge (WCJ) granted the petition and determined that the claimant lost the use of his right eye for all practical intents and purposes, that his right eye did not contribute materially to his vision in conjunction with the left eye, and found a disfigurement of the right eye, for which he ordered 50 weeks of benefits. The employer appealed to the Workers’ Compensation Appeal Board (Board) and the Board affirmed, but with a remand to the WCJ for reconsideration of the disfigurement award. On remand, the WCJ again awarded 50 weeks of disfigurement benefits. The Board affirmed on appeal, and the employer appealed to the Commonwealth Court. The employer made a number of arguments on appeal to the Commonwealth Court. Firstly, the employer argued that the WCJ’s decision was not well reasoned or supported by substantial evidence because the WCJ, on remand, inaccurately summarized the claimant’s testimony after previously finding that the claimant lied four times under oath about a pre-existing right eye vision loss. The Court rejected this argument, finding no error by the WCJ, as she explained her credibility determinations and her decision was supported by the testimony of the medical experts in the case. Secondly, the employer argued that the WCJ erred by awarding specific loss benefits for vision loss, because the claimant was legally blind in the same right eye before the work incident. The Court rejected this argument, however, finding that the WCJ correctly concluded that the claimant’s use of his injured eye did not contribute materially to his vision in conjunction with his normal eye. Lastly, the Court rejected an argument made by the employer that the award of 275 weeks for benefits from vision loss should be apportioned to 10% or 27.5 weeks, since the claimant had less than 10% vision in his right eye before the work injury. The Court said there was no supportive legal argument or citation to legal authority for this argument. 

Thought Leadership

Appellate Division Affirmed Workers’ Compensation Judge’s Decision of Permanency

In Lawhon v. Cnty of Monmouth, the respondent, County of Monmouth, appealed a workers’ compensation decision, finding permanency of 55% partial-total minus a 31% prior injury credit. By way of background, on October 4, 2021, the petitioner injured his back while working for the respondent. He also worked part-time at Home Depot around 2023 to make ends meet because his wife lost her job. The judge found his explanation reasonable as to why he was working a second job despite his injury. Prior to this accident, in 2013, the petitioner had injured his back at work and had a prior permanency award of 22.5% partial-total. A few months prior to this accident, that case was re-opened in July 2021, resulting in an increased award to 31% partial-total. The only issue at trial for this case was the nature and extent of permanency. The respondent argued the petitioner’s disability to the 2013 accident significantly overlapped to this instant case, including inability to lift over 100 pounds, taking Aleve for pain, trouble walking, climbing stairs, and difficulty with sleep and household chores. The respondent argued that the judge did not distinguish between the 2013 and 2021 accidents. After the 2013 accident, the petitioner had one spinal fusion surgery. Then, after the 2021 accident, he underwent 2 additional lumbar fusions, injections, and a discectomy. He eventually had a permanent spinal cord stimulator implanted. The petitioner testified that after the 2021 accident, his ability to work slowed down and that he would get tired faster. He could no longer lift up to 100 pounds and that even while working for Home Depot, he refrained from lifting anything heavy or received help from co-workers. He indicated that he was in constant pain while working for the respondent and Home Depot, which was not the case prior to the 2021 injury. He also testified as to his inability to do daily activities, difficulty sleeping despite purchasing a better/more expensive bed, and not going out with friends or doing certain activities. The workers’ compensation judge found the petitioner’s testimony to be credible and despite a surveillance video produced by the respondent, the judge noted that it did not reveal any tasks that the petitioner testified he could not do. As for the experts, the petitioner’s expert, Dr. Alan Nasar, provided his diagnoses regarding the 2021 incident and found a 50% additional permanency over the prior 31% award for the lumbar spine and 30% permanency for the thoracic spine. On the other hand, Dr. Peacock found the petitioner had degenerative arthritis, degenerative disc disease, and protrusion and found 10% disability, apportioned 2.5% for the 2021 accident. The judge indicates that while he found both experts to be credible, he found Dr. Nasar to be more credible, noting some concerns with Dr. Peacock’s testimony, exam, and curriculum vitae, stating that he did not practice as a treating physician beyond 1995. The respondent appealed and the Appellate Division affirmed the workers’ compensation decision on the finding of permanent disability. Specifically, the Appellate Division noted that the judge found the petitioner satisfied the Perez requirements. First, the petitioner showed demonstrable objective medical evidence that his functioning had decreased. He also proved there was a material lessening of his working ability as well as impact on his ordinary pursuits in life. Overall, the Appellate Division noted that the judge’s findings and conclusions were supported by credible evidence.