3rd District Analyzes Liquidated Damages Provision, Contingency Risk Multiplier in Context of Construction Contract

Alan Kent Little v. Bath & Kitchen Boutique, LLC, 51 Fla. L. Weekly D1073 (Fla. 3rd DCA, May 27, 2026)

July 21, 2026

by Nathan R. Woods

Alan Little and Bath & Kitchen Boutique, LLC (BKB) entered into an agreement wherein BKB would design and renovate Little’s master bathroom. A portion of BKB’s work failed to pass city inspections, after which the parties executed a contract amendment giving BKB additional time to pass final inspection and establishing that BKB would owe Little $1,000 per day for each day it went beyond this additional time. The amendment also contained a provision requiring BKB to pay 100% of Little’s legal fees for preparing the amendment and enforcing it. BKB’s work ultimately passed final inspection 67 days beyond the amendment’s completion date.

Little then filed suit against BKB alleging breach of contract and seeking $67,000 in liquidated damages. BKB filed countersuit alleging it was entitled to a judgment declaring the $1,000 per day fine to be an unenforceable penalty, and that Little had breached the agreement by failing to pay BKB for its work. Both parties alleged entitlement to attorneys’ fees based on the fee provision in the amendment, with BKB alleging the provision was reciprocal pursuant to Fla. Stat. 57.105(7).

Little obtained the issuance of a $35,000 prejudgment writ of garnishment. BKB moved to dissolve the writ. Two hearings were held on BKB’s motion, but the court never issued final adjudication. Little then filed a notice extending the writ for an additional six months.

BKB filed a petition for writ of certiorari challenging the lower court’s discovery order, which was granted. Both parties filed motions for appellate level fees based on the fee provision, and the appeals court then denied Little’s appellate fees motion and conditionally granted BKB’s, provided BKB prevailed in the trial court action and the trial court found the fee provision valid.

Both parties then filed competing summary judgment motions in the lower court, which entered partial summary judgment in BKB’s favor, concluding the daily fine was unenforceable. The parties entered a settlement agreement as to BKB’s remaining counterclaim seeking payment for its work, with Little stipulating to BKB’s entitlement to attorney’s fees and costs and requesting an evidentiary hearing to set the amount of fees and costs.

A two-day evidentiary hearing was held with the court considering live testimony from BKB’s owner, trial attorney, and fees expert. The court then awarded BKB attorney’s fees for the time spent litigating issues relating to the prejudgment writ of garnishment, at both trial and appellate levels, pursuant to Fla. Stat. 77.032(3) and 57.105(7). It applied a 1.5 contingency risk multiplier. Little then appealed.

On appeal, the court analyzed Fla. Stat. 57.105(7), and specifically its use of the language “with respect to the contract,” through the lens of the FL Supreme Court’s opinion in Ham v. Portfolio Recovery Associates, LLC. The Ham court found that even actions that are not “based on” or “pursuant to” the underlying contract may still have a clear and direct relationship so as to fit the statute’s language. Here, the court similarly found there was a clear and direct relationship between the proceedings on Little’s writ and the parties’ contract litigation.

However, as to the contingency risk multiplier, the court found that BKB did not offer any direct evidence that, absent availability of a contingency risk multiplier, BKB would have faced substantial difficulty finding an attorney to represent it. BKB merely argued that construction attorneys in the relevant market rarely took on breach of contract actions under a contingency fee. As such, the contingency fee instituted by the trial court was not supported by the requisite evidence and thus improper.

The court therefore affirmed the award of costs and fees to BKB, but reversed the application of the contingency risk multiplier to the fees award and remanded for amended judgment consistent with this opinion.

Firm Highlights

Thought Leadership

Employer Not Entitled to Increase Social Security Retirement Benefit Offset Based on Social Security Cost of Living Adjustments

This case involved a claimant who sustained a work injury in 1997, which the employer accepted. The claimant began receiving Social Security Retirement (SSR) benefits in March 2017, and the employer began reducing those benefits under Section 204(a) of the Act. The claimant subsequently received Cost of Living Adjustments (COLA) to her SSR Benefits, and each time, the employer increased its offset, without challenge by the claimant, until 2023, when the claimant filed a Petition to Review Benefit Offset. The WCJ granted the petition, concluding that the offset in Section 204(a) is set at the time the SSR benefit is received, and should not be readjusted based on SSR COLA increases. The employer appealed, and the Board reversed, interpreting Section 204(a) to unambiguously allowing the offset of 50% of all SSR benefits. According to the Board, they could not read into the offset language of the Act an exception for COLA increases to Social Security offsets, where no such language existed. The claimant appealed to the Commonwealth Court, and the Court reversed the Board. In doing so, the Court held that the Board’s interpretation of Section 204(a), permitting the employer to increase its offset based on the claimant’s receipt of a COLA increase to her SSR benefits, was contrary to the intent of the General Assembly, the intent of the United States Congress and the humanitarian purpose of the Act. The Court pointed out that the purpose of the 1996 amendment to the Act relative to offsets for SSR benefits was to provide reasonable cost containment for employers and should not be used to allow employers to obtain a windfall by receiving credit for amounts not intended by the General Assembly.

Thought Leadership

WCJ Cannot Apportion an Award of Benefits for Vision Loss Based on the Percentage of Vision Loss that Existed Before the Work Injury

In this case, the claimant filed a Claim Petition alleging that he suffered a work injury to his right eye. The Workers’ Compensation Judge (WCJ) granted the petition and determined that the claimant lost the use of his right eye for all practical intents and purposes, that his right eye did not contribute materially to his vision in conjunction with the left eye, and found a disfigurement of the right eye, for which he ordered 50 weeks of benefits. The employer appealed to the Workers’ Compensation Appeal Board (Board) and the Board affirmed, but with a remand to the WCJ for reconsideration of the disfigurement award. On remand, the WCJ again awarded 50 weeks of disfigurement benefits. The Board affirmed on appeal, and the employer appealed to the Commonwealth Court. The employer made a number of arguments on appeal to the Commonwealth Court. Firstly, the employer argued that the WCJ’s decision was not well reasoned or supported by substantial evidence because the WCJ, on remand, inaccurately summarized the claimant’s testimony after previously finding that the claimant lied four times under oath about a pre-existing right eye vision loss. The Court rejected this argument, finding no error by the WCJ, as she explained her credibility determinations and her decision was supported by the testimony of the medical experts in the case. Secondly, the employer argued that the WCJ erred by awarding specific loss benefits for vision loss, because the claimant was legally blind in the same right eye before the work incident. The Court rejected this argument, however, finding that the WCJ correctly concluded that the claimant’s use of his injured eye did not contribute materially to his vision in conjunction with his normal eye. Lastly, the Court rejected an argument made by the employer that the award of 275 weeks for benefits from vision loss should be apportioned to 10% or 27.5 weeks, since the claimant had less than 10% vision in his right eye before the work injury. The Court said there was no supportive legal argument or citation to legal authority for this argument. 

Thought Leadership

Appellate Division Affirmed Workers’ Compensation Judge’s Decision of Permanency

In Lawhon v. Cnty of Monmouth, the respondent, County of Monmouth, appealed a workers’ compensation decision, finding permanency of 55% partial-total minus a 31% prior injury credit. By way of background, on October 4, 2021, the petitioner injured his back while working for the respondent. He also worked part-time at Home Depot around 2023 to make ends meet because his wife lost her job. The judge found his explanation reasonable as to why he was working a second job despite his injury. Prior to this accident, in 2013, the petitioner had injured his back at work and had a prior permanency award of 22.5% partial-total. A few months prior to this accident, that case was re-opened in July 2021, resulting in an increased award to 31% partial-total. The only issue at trial for this case was the nature and extent of permanency. The respondent argued the petitioner’s disability to the 2013 accident significantly overlapped to this instant case, including inability to lift over 100 pounds, taking Aleve for pain, trouble walking, climbing stairs, and difficulty with sleep and household chores. The respondent argued that the judge did not distinguish between the 2013 and 2021 accidents. After the 2013 accident, the petitioner had one spinal fusion surgery. Then, after the 2021 accident, he underwent 2 additional lumbar fusions, injections, and a discectomy. He eventually had a permanent spinal cord stimulator implanted. The petitioner testified that after the 2021 accident, his ability to work slowed down and that he would get tired faster. He could no longer lift up to 100 pounds and that even while working for Home Depot, he refrained from lifting anything heavy or received help from co-workers. He indicated that he was in constant pain while working for the respondent and Home Depot, which was not the case prior to the 2021 injury. He also testified as to his inability to do daily activities, difficulty sleeping despite purchasing a better/more expensive bed, and not going out with friends or doing certain activities. The workers’ compensation judge found the petitioner’s testimony to be credible and despite a surveillance video produced by the respondent, the judge noted that it did not reveal any tasks that the petitioner testified he could not do. As for the experts, the petitioner’s expert, Dr. Alan Nasar, provided his diagnoses regarding the 2021 incident and found a 50% additional permanency over the prior 31% award for the lumbar spine and 30% permanency for the thoracic spine. On the other hand, Dr. Peacock found the petitioner had degenerative arthritis, degenerative disc disease, and protrusion and found 10% disability, apportioned 2.5% for the 2021 accident. The judge indicates that while he found both experts to be credible, he found Dr. Nasar to be more credible, noting some concerns with Dr. Peacock’s testimony, exam, and curriculum vitae, stating that he did not practice as a treating physician beyond 1995. The respondent appealed and the Appellate Division affirmed the workers’ compensation decision on the finding of permanent disability. Specifically, the Appellate Division noted that the judge found the petitioner satisfied the Perez requirements. First, the petitioner showed demonstrable objective medical evidence that his functioning had decreased. He also proved there was a material lessening of his working ability as well as impact on his ordinary pursuits in life. Overall, the Appellate Division noted that the judge’s findings and conclusions were supported by credible evidence.