Adam is a member of the firm's Architectural, Engineering & Construction Defect Litigation Practice Group. He concentrates his practice in complex construction defect matters, which include the defense of contractors, architects, engineers, surveyors and other professionals. He also defends claims of bodily injury, property damage, delay damages and other claims related to the construction industry.

In complex multiparty litigation, Adam has developed significant experience. He has successfully represented clients in matters involving wrongful death, school construction defects, condominium construction defects, public entity construction projects, and geotechnical engineering, including inaccurate surveying claims, improper dynamic compaction claims, and various other claims of deviations from architectural and engineering standards of care.

Adam earned his Bachelor of Arts Degree from Stockton State College and his juris doctor from The Thomas M. Cooley Law School. 

    • Cooley Law School (J.D., 1996)
    • Stockton University (B.A., 1990)
    • New Jersey, 1997
    • U.S. District Court District of New Jersey
    • Pennsylvania, 1996
    • Successfully defended client through a two and a half month trial, with a no cause of action verdict against a products defect claim which allegedly resulted in burns to over 58% of plaintiff's body.  The case involved claims against a major U.S. car manufacturer as well as an internationally recognized automotive organization.  On the eve of closing arguments, the other parties settled without notice to Adam or his client.  The last demand on Adam’s client was for tender of its $10 Million Policy.
    • Obtained a jury verdict on behalf of insurer in favor of carrier on an insurance fraud claim.  Plaintiff in this matter fraudulently accepted payment from both a tortfeasor’s automotive carrier and his own carrier, effectively “double-dipping” to receive duplicative recoveries.  Adam successfully obtained a verdict recovering for the carrier its payment with treble damages for the defendant’s violation of the New Jersey Insurance Fraud Act.
    • Successfully represented major amusement park owner through trial in defense of a juvenile death case.  Representation included Supreme Court submissions and appearances prior to trial.  Results included seminal Supreme Court decision on the allocation of liability on behalf of the client as against a sovereign entity that was dismissed from the case due to the plaintiff’s failure to add the sovereign as a direct defendant prior to the expiration of the notice provisions of the torts claim act.  Based on our representation, the jury would be instructed to allocate liability for the sovereign’s negligence thus offsetting any potential negligence against the client.
    • Obtained summary judgment for a national engineering firm against claims of personal injury to a construction worker injured on a job site.  Issues related Affidavit of Merit Statute and its applicability to client’s field representative’s scope of work during the construction of a multi-million dollar U.S. Coast Guard facility.
    • Obtained summary judgement for a major national residential home developer against claims of personal injury by a construction worker injured on a job site.  Issues related to the scope of client’s involvement in the construction of a planned urban development. 
    • Obtained dismissal of claims against a major national residential home developer arising out of alleged defects in the construction of a multi-million dollar home.  Also recouped all costs and fees related to the client’s defense based on contractual indemnifications from co-defendant.
    • Obtained summary judgement for a major regional residential homebuilder against claims of construction defect arising out of damages to multi-million dollar beachfront home caused during Hurricane Sandy.
    • Obtained summary judgment for a developer and general contractor in a construction defect case. The plaintiff, a homeowners association, sued multiple parties seeking $2.5 million in damages related to water infiltration due to the allegedly negligent installation of roofing, exterior cladding, windows, doors, railings and decks. We also represented several previous developer/association board members who were sued individually. Prior to filing suit, the plaintiff filed a claim with the state of New Jersey under the Home Owners Warranty program.
    • Obtained dismissal of all claims against major energy company related to death claim. Deceased’s estate alleged that client was implicated in an alleged failure to provide safety on the roof of a construction site which resulted in the deceased falling through roof to his death.

Results

Thought Leadership

Case Law Alerts

The Lack of a Retainage Payment to General Contractor Did Not Bar Payment to the General Contractor's Subcontractors, Regardless of a Condition Precedent Requiring that the General Contract be Paid Before the Subcontractors

July 1, 2023

As addressed in the unreported case of J &M Interiors, Inc. v. Centerton Square Owners, LLC, (A-2536-19, 2021 WL 1976648 (N.J. Super. Ct. App. Div. May 18, 2021), the lack of a retainage payment to a general contractor (GC) did not bar payment to the GC’s subcontractors, regardless of a condition precedent requiring that the GC be paid before the subcontractors. This “condition precedent” has been dubbed a “pay-if-paid” provision. Seeing such a provision as a matter of first impression in this case, the court has confirmed that “pay-if-paid” provisions in construction contracts are enforceable “as long as the contract on its face contains clear and unequivocal language that unambiguously sets forth the parties’ intention and agreement that owner payment is a condition precedent to the general contractor's obligation to pay the subcontractor.” Thus, the risk of payment is shifted to the subcontractors, unless the GC has “prevented or hindered” the owner’s payment, which would shift the onus back to the GC. Case Law Alerts, 3rd Quarter, July 2023 is prepared by Marshall Dennehey to provide information on recent developments of interest to our readers. This publication is not intended to provide legal advice for a specific situation or to create an attorney-client relationship. Copyright © 2023 Marshall Dennehey, all rights reserved. This article may not be reprinted without the express written permission of our firm.

Case Law Alerts

New Jersey Extends the Statute of Limitations in Construction Cases Involving Planned Real Estate Development Associations

July 1, 2022

N.J.S.A. 2A:14-1 has been amended to add a new subsection. The addition provides that the timing of a claim filed by a planned real estate development association is tolled “until an election is held and the owners comprise a majority of the board.” This extends the prior statute of limitations for a construction defect claim (not arising from an unsafe condition) which was calculated at six years from the date of substantial completion of the planned real estate development project. The new law tolls the time for an association “acting through, on behalf of, or at the behest of the developer,” but it does not expressly toll it for claims against subcontractors.  In a practical sense, the expiration of the statute of limitations for claims against a general contractor and/or its subcontractors can thereby occur before accrual of an association’s claims. Regardless, a developer would not be able to take advantage of the tolling of time to bring related claims (contractual and/or tort) against its own contractors if the association does not sue the contractor/subs directly.   Case Law Alerts, 3rd Quarter, July 2022 is prepared by Marshall Dennehey Warner Coleman & Goggin to provide information on recent developments of interest to our readers. This publication is not intended to provide legal advice for a specific situation or to create an attorney-client relationship. Copyright © 2022 Marshall Dennehey Warner Coleman & Goggin, all rights reserved. This article may not be reprinted without the express written permission of our firm.

Firm Highlights

Thought Leadership

Appellate Division Affirmed Workers’ Compensation Judge’s Decision of Permanency

In Lawhon v. Cnty of Monmouth, the respondent, County of Monmouth, appealed a workers’ compensation decision, finding permanency of 55% partial-total minus a 31% prior injury credit. By way of background, on October 4, 2021, the petitioner injured his back while working for the respondent. He also worked part-time at Home Depot around 2023 to make ends meet because his wife lost her job. The judge found his explanation reasonable as to why he was working a second job despite his injury. Prior to this accident, in 2013, the petitioner had injured his back at work and had a prior permanency award of 22.5% partial-total. A few months prior to this accident, that case was re-opened in July 2021, resulting in an increased award to 31% partial-total. The only issue at trial for this case was the nature and extent of permanency. The respondent argued the petitioner’s disability to the 2013 accident significantly overlapped to this instant case, including inability to lift over 100 pounds, taking Aleve for pain, trouble walking, climbing stairs, and difficulty with sleep and household chores. The respondent argued that the judge did not distinguish between the 2013 and 2021 accidents. After the 2013 accident, the petitioner had one spinal fusion surgery. Then, after the 2021 accident, he underwent 2 additional lumbar fusions, injections, and a discectomy. He eventually had a permanent spinal cord stimulator implanted. The petitioner testified that after the 2021 accident, his ability to work slowed down and that he would get tired faster. He could no longer lift up to 100 pounds and that even while working for Home Depot, he refrained from lifting anything heavy or received help from co-workers. He indicated that he was in constant pain while working for the respondent and Home Depot, which was not the case prior to the 2021 injury. He also testified as to his inability to do daily activities, difficulty sleeping despite purchasing a better/more expensive bed, and not going out with friends or doing certain activities. The workers’ compensation judge found the petitioner’s testimony to be credible and despite a surveillance video produced by the respondent, the judge noted that it did not reveal any tasks that the petitioner testified he could not do. As for the experts, the petitioner’s expert, Dr. Alan Nasar, provided his diagnoses regarding the 2021 incident and found a 50% additional permanency over the prior 31% award for the lumbar spine and 30% permanency for the thoracic spine. On the other hand, Dr. Peacock found the petitioner had degenerative arthritis, degenerative disc disease, and protrusion and found 10% disability, apportioned 2.5% for the 2021 accident. The judge indicates that while he found both experts to be credible, he found Dr. Nasar to be more credible, noting some concerns with Dr. Peacock’s testimony, exam, and curriculum vitae, stating that he did not practice as a treating physician beyond 1995. The respondent appealed and the Appellate Division affirmed the workers’ compensation decision on the finding of permanent disability. Specifically, the Appellate Division noted that the judge found the petitioner satisfied the Perez requirements. First, the petitioner showed demonstrable objective medical evidence that his functioning had decreased. He also proved there was a material lessening of his working ability as well as impact on his ordinary pursuits in life. Overall, the Appellate Division noted that the judge’s findings and conclusions were supported by credible evidence.

Thought Leadership

Employer Not Entitled to Increase Social Security Retirement Benefit Offset Based on Social Security Cost of Living Adjustments

This case involved a claimant who sustained a work injury in 1997, which the employer accepted. The claimant began receiving Social Security Retirement (SSR) benefits in March 2017, and the employer began reducing those benefits under Section 204(a) of the Act. The claimant subsequently received Cost of Living Adjustments (COLA) to her SSR Benefits, and each time, the employer increased its offset, without challenge by the claimant, until 2023, when the claimant filed a Petition to Review Benefit Offset. The WCJ granted the petition, concluding that the offset in Section 204(a) is set at the time the SSR benefit is received, and should not be readjusted based on SSR COLA increases. The employer appealed, and the Board reversed, interpreting Section 204(a) to unambiguously allowing the offset of 50% of all SSR benefits. According to the Board, they could not read into the offset language of the Act an exception for COLA increases to Social Security offsets, where no such language existed. The claimant appealed to the Commonwealth Court, and the Court reversed the Board. In doing so, the Court held that the Board’s interpretation of Section 204(a), permitting the employer to increase its offset based on the claimant’s receipt of a COLA increase to her SSR benefits, was contrary to the intent of the General Assembly, the intent of the United States Congress and the humanitarian purpose of the Act. The Court pointed out that the purpose of the 1996 amendment to the Act relative to offsets for SSR benefits was to provide reasonable cost containment for employers and should not be used to allow employers to obtain a windfall by receiving credit for amounts not intended by the General Assembly.

Thought Leadership

WCJ Cannot Apportion an Award of Benefits for Vision Loss Based on the Percentage of Vision Loss that Existed Before the Work Injury

In this case, the claimant filed a Claim Petition alleging that he suffered a work injury to his right eye. The Workers’ Compensation Judge (WCJ) granted the petition and determined that the claimant lost the use of his right eye for all practical intents and purposes, that his right eye did not contribute materially to his vision in conjunction with the left eye, and found a disfigurement of the right eye, for which he ordered 50 weeks of benefits. The employer appealed to the Workers’ Compensation Appeal Board (Board) and the Board affirmed, but with a remand to the WCJ for reconsideration of the disfigurement award. On remand, the WCJ again awarded 50 weeks of disfigurement benefits. The Board affirmed on appeal, and the employer appealed to the Commonwealth Court. The employer made a number of arguments on appeal to the Commonwealth Court. Firstly, the employer argued that the WCJ’s decision was not well reasoned or supported by substantial evidence because the WCJ, on remand, inaccurately summarized the claimant’s testimony after previously finding that the claimant lied four times under oath about a pre-existing right eye vision loss. The Court rejected this argument, finding no error by the WCJ, as she explained her credibility determinations and her decision was supported by the testimony of the medical experts in the case. Secondly, the employer argued that the WCJ erred by awarding specific loss benefits for vision loss, because the claimant was legally blind in the same right eye before the work incident. The Court rejected this argument, however, finding that the WCJ correctly concluded that the claimant’s use of his injured eye did not contribute materially to his vision in conjunction with his normal eye. Lastly, the Court rejected an argument made by the employer that the award of 275 weeks for benefits from vision loss should be apportioned to 10% or 27.5 weeks, since the claimant had less than 10% vision in his right eye before the work injury. The Court said there was no supportive legal argument or citation to legal authority for this argument.