Defense Digest

Pennsylvania Supreme Court Expands Liability of Contractors for Completed Work – Even If a Defect Is Obvious

Defense Digest, Vol. 29, No. 3, September 2023

September 1, 2023

Key Points:

  • The Supreme Court of Pennsylvania held that a contractor can be liable for a hazardous condition it created, even if the work is accepted, known by the property owner, and is obvious in nature.
  • This opens the door to remote claims brought by third parties against construction contractors.
  • It may serve to undercut the open and obvious defense to claims brought by the public against out-of-possession contractors.
  • This does not serve to relieve premises owners/possessors of potential joint liability with contractors.

In Brown v. City of Oil City, 294 A.3d 413 (Pa. May 16, 2023), the City of Oil City, Pennsylvania, retained two contractors to design and oversee reconstruction of the deteriorated concrete stairs leading to the entrance of the City’s library. The work was performed by another contractor, also through a contract with the City. Installation of the new stairs was completed by the end of 2011. However, in early 2012, the City received reports about imperfections in the concrete surface. The City notified the contractors that it considered the steps to be dangerous and defective. Between 2012 and 2015, the condition became worse, but no remedial work was performed. In 2015, the plaintiff exited the library, tripped on one of the deteriorated steps, and sustained a fatal head trauma. A wrongful death suit was filed against the City and the contractors.

After discovery, the contractors were granted summary judgment, having argued they owed no duty to third persons as they were not in possession of the premises at the time of injury. The trial court cited to Section 385 of the Restatement (Second) of Torts as limiting a contractor’s third-party liability to only those situations where a possessor was unlikely to discover the defect. The court relied on Gresik v. PA Partners, L.P., 989 A.2d 344 (Pa. Super. 2009) (Gresik I), which involved a negligence suit against the prior owner of a steel plant where modifications had been made. The prior owner removed a drawbridge designed as a safety feature for steelworkers. After the plant was sold, a steelworker died when he had no means of escaping a molten steel breach. Suit was brought against the prior owner. The Superior Court held that a precondition for liability under Section 385 is showing that the danger was unlikely to be discovered by the possessor. Since the plant’s current owner was aware of the hazard, summary judgment was entered for the prior owner. Citing to Gresik I, the trial court in Brown held that the contractors could not be liable because the City was aware of the hazardous condition of the steps. 

The Commonwealth Court reversed, citing two Pennsylvania cases that imposed liability on contractors to the public, Prost v. Caldwell Stores, 187 A.2d 273 (Pa. 1963) and Gilbert v. Conrail, 623 A.2d 873 (Pa. Cmwlth. 1963). In Prost, the court held that a contractor could be liable to third parties for faulty tile installation, despite the possessor’s acceptance of the work. In Gilbert, Conrail built a defectively designed track crossing and then turned the property over to SEPTA. Despite the obvious nature of the track crossing, the court in Gilbert held that Conrail could still be liable for a passenger’s death resulting from the hazard and that the the condition did not have to be hidden, or latent, for the contractor to be liable. SEPTA’s awareness of the condition did not negate Conrail’s exposure. 

The contractors in Brown argued on appeal to the Supreme Court that the court should adopt the Superior Court’s approach in Gresik I to limit liability for an out-of-possession contractor to latent defects only. They argued that since the condition of the steps was known by the City, that entity was solely responsible for remediation. In fact, the contractors argued that they could not take action without instructions from the City. The City would be in the best position to remedy defects, instead of a contractor who no longer had contact with the property. They also cited to the Restatement under which possessors are required to inspect for latent defects to protect invitees. Further, they cited to a comment of Section 385, which imposed liability on contractors only to the same extent as manufacturers of a product, that is, for defects which the end user is not able to discover. Brown, to the contrary, argued that Section 385 does not pre-condition a contractor’s liability to third parties on the knowledge of the possessor. Brown further argued that the contractor’s interpretation creates an incentive for possessors to ignore defects and that the possessor’s knowledge should not insulate the contractor. 

The Supreme Court in Brown affirmed the Commonwealth Court’s reversal of summary judgment. The court sided with the reasoning of Gilbert, which permitted liability, even for open and obvious conditions known by the possessor. The court held that under Section 385 of the Restatement, a contractor could face liability whether the condition was latent or apparent. 

The Supreme Court interpreted Section 385 as imposing liability on contractors for injuries to third parties arising from all defects, whether latent or obvious. The court noted that comment c to Section 385, which refers to work “unlikely to be discovered by the possessor,” is not applicable to third parties, but only relates to claims brought by possessors. As such, under Brown, a contractor can be found liable to third parties as a result of a dangerous condition it created, regardless of whether the condition is latent, open and obvious, or known by the possessor. If the condition is latent, a possessor may have a viable claim as well. This decision only bars a claim by a possessor against a contractor for an open and obvious condition. The court also notes that a possessor also retains a duty to keep its premises reasonably safe for third parties and could be jointly liable with a contractor. 

This case is problematic as it opens the door to injury claims brought against contractors by third parties long after their work is accepted, even if the condition is open and obvious to the plaintiff and the possessor. Also, the court does not address the established defenses that no duty is owed to warn of open and obvious conditions, or that the plaintiff may be at fault for assuming a risk. Last, it is presumed that this decision does not impact a statute of repose defense, assuming a defendant fits within the protected class. 

*David is an Of Counsel and works in our Philadelphia, Pennsylvania, office. He can be reached at 215.575.3577 or dswolf@mdwcg.com. 


 

Defense Digest, Vol. 29, No. 3, September 2023, is prepared by Marshall Dennehey to provide information on recent legal developments of interest to our readers. This publication is not intended to provide legal advice for a specific situation or to create an attorney-client relationship. ATTORNEY ADVERTISING pursuant to New York RPC 7.1. © 2023 Marshall Dennehey. All Rights Reserved. This article may not be reprinted without the express written permission of our firm. For reprints, contact tamontemuro@mdwcg.com.

Firm Highlights

Thought Leadership

Delaware Superior Court Clarifies Pleading Standard for Legal Malpractice Claims

In the matter of Edelstein v. Kirschner, No. N25C-09-018 FJJ, 2026 Del. Super. LEXIS 45, at *1 (Super. Ct. Jan. 29, 2026), the plaintiff law firm sued its former client for unpaid legal fees in the amount of $4,399.35. The former client asserted a counterclaim alleging legal malpractice. More, specifically, the former client claimed that his lawyer committed malpractice be recommending that he settle an underlying lawsuit by entering into a stipulated judgment for an excessive amount with interest that was accruing at “an outlandish” interest rate. The law firm moved to dismiss the counterclaim on the basis that its former client had not alleged facts reflecting that he could prove the case within the case. That is, facts reflecting that his attorneys caused him to lose the underlying case. The Superior Court held that while a legal malpractice plaintiff in cases arising from underlying litigation must prove the case within the case to survive a summary judgment motion, he does not need to plead facts reflecting as much in order to survive a motion to dismiss. While this case addresses the pleading requirements of a legal malpractice case in Delaware, it also serves as reminder that chasing unpaid legal fees from a former client can often give rise to a legal malpractice counterclaim. Attorneys seeking to collect unpaid legal fees should ensure that the fees they seek are for a significant amount, which would be recoverable if a judgment is obtained. Otherwise, the effort could backfire.

Thought Leadership

Appellate Division Affirms Dismissal of Legal Malpractice Counterclaim Against Martin Law Firm

In Martin v. Loury, 2026 N.J. Super. Unpub. LEXIS 1617 (App. Div. July 15, 2026), Martin Law Firm represented Kirk Loury in an employment matter Mr. Loury filed against his former employer, Concord Equity Group Advisors LLC (“Concord”). The allegations included, among other things, that Loury was not fairly compensated for his employment with Concord. After a bench trial finding in Loury’s favor, the Appellate Division remanded this matter in February 2016 for a second trial. During the second trial, Concord CEO, Lee Argush, testified to lower compensation estimate than first trial. On remand, the second trial judge awarded Mr. Loury the same damages as the first judge, finding Mr. Argush not credible. After the findings during the second trial, Martin Law Firm filed an action against Mr. Loury to recover legal fees and costs of representing Mr. Loury in a second bench trial and Mr. Loury filed a counterclaim against Martin Law Firm for legal malpractice, alleging he should have received an even higher award in the second bench trial. In this allegation, Mr. Loury, through his expert, claimed that Martin Law Firm should have recalled Mr. Loury to the stand to rebut Mr. Argush’s testimony to allege an alternative theory of damages. Mr. Loury’s expert admitted that the second judge already rejected Mr. Argush's theory and accepted Loury's damages theory. The trial court barred Mr. Loury’s expert and dismissed Loury's counterclaim with prejudice before convening the collection trial, and the jury ruled in Martin Law Firm’s favor. Mr. Loury appealed the trial court's pretrial rulings barring his liability expert from testifying in support of his legal malpractice counterclaim, denying his motion for summary judgment on that counterclaim, and denying his motion to amend his counterclaim by adding attorney Joseph A. Martin as a codefendant. In affirming the trial court’s decision, the Appellate Division held that the trial court properly excluded Loury’s expert testimony in the counterclaim against Martin Law Firm because the expert could not explain how calling Loury as a rebuttal witness would have increased damages when the second judge already rejected Mr. Argush's testimony and accepted Loury's damages theory, making the expert’s causation opinion speculative. The Appellate Division also held that the trial court properly denied Mr. Loury's summary judgment motion on his malpractice counterclaim because reasonable minds could differ on whether Mr. Martin's alleged failures would have changed the second judge's damages award, given the judge already found Mr. Argush not credible, creating genuine factual disputes precluding summary judgment. Also, the Appellate Division held that the trial court properly denied Loury's May 2023 motion to add Joseph Martin individually because the statute of limitations expired in February 2022, six years after the 2016 appellate remand when Mr. Loury incurred new legal costs, and relation back did not apply because Mr. Loury knew Mr. Martin's identity throughout and strategically chose to sue only Martin Law Firm in his 2019 counterclaim.