.

Case Law Alerts

Contractor Prevails on Contractual Risk of Loss Provision

Berman Construction & Development, Inc. v. Carnaval Home, LLC, et al., Case No. 4D2024-2174 (4th Dist., April 22, 2026)

July 21, 2026

by Nathan R. Woods

Carnaval Home hired Berman Construction to renovate an existing home owned by Carnaval. Their contract set the date of substantial completion at September 4, 2019, and included a risk of loss provision placing risk predominantly on Carnaval. Berman hired subcontractors, including an electrician and project supervisor, to carry out the renovations.

On July 29, 2019, with renovation 90% complete, a fire destroyed the home. Carnaval then sued Berman for breach of contract, negligence, and violation of Florida building code. Carnaval based its breach of contract theory primarily on Berman failing to deliver the renovated property by substantial completion. At trial, Carnaval presented evidence that faulty attic wiring caused the fire, while Berman claimed it was caused by arson or another cause beyond its control. During the charge conference, Berman requested a question on the verdict form regarding the risk of loss provision and its other defenses of impossibility of performance and frustration of purpose.

The trial court granted a directed verdict on impossibility of performance and frustration of purpose, holding the risk of loss provision eliminated those defenses, and also denied Berman’s request for the risk of loss question on the verdict form. The verdict form ultimately included questions regarding the breach, negligence, and code violation claims. Its questions regarding the breach claim included the following: whether Carnaval did what was required by contract; whether Carnaval was excused from doing what was required by contract; whether Berman failed to do what was required by contract; and whether Carnaval was damaged by Berman’s failure to perform. The jury found Berman was not negligent but did violate the building code and breach its contract, though the code violation did not cause Carnaval’s damages. Carnaval was awarded $928,850 pursuant to the breach claim. The trial court denied Berman’s post-trial motions and granted Carnaval’s motion for attorneys fees.

On appeal, the 4th DCA noted that Carnaval presented evidence that the fire occurred the day electrical work was completed and power was restored to the house for the first time since construction began, when the home was under the exclusive control of Berman and its subcontractors. It presented testimony from the carpenter that the kitchen and family room lights went out while he was at the property that evening, which was also corroborated by Carnaval principal Luis Ormo. It presented expert testimony that the fire likely started in the attic and was not a result of arson. Berman offered testimony that traces of gas were detected along with unusual burn patterns and heat deformation at the bottom of door frames. Its expert testified that the fire had multiple points of origin. Berman established the home was engulfed in flames emanating from the roof within twenty minutes of Carnaval leaving the property and argued the fire could not have moved so fast absent arson. It further suggested the electrician and Ormo had separate dealings in violation of their subcontract, thus some of the electrician’s conduct was beyond Berman’s control.

The 4th DCA held Berman’s claim of inconsistency between the negligence, building code violation, and breach jury verdicts was to be remedied by a new trial, not directed verdict, and further held that it did not have to decide whether the verdict was truly inconsistent as Berman did not raise this issue before the jury was discharged and did not seek the appropriate remedy of a new trial. As such, it held the trial court was correct in denying Berman’s motion for directed verdict.

However, the court held that the trial court erred in denying Berman’s special interrogatory request as to the risk of loss provision. It explained that, where interrogatory verdict forms are used, it should include questions on both the plaintiff’s claims and any affirmative defenses. Without allowing a question regarding whether the risk of loss provision excused Berman from performance, the trial court did not resolve “the major question in the case.” The jury, having found Berman not negligent, made Berman’s defense, and the verdict form question, particularly significant. The court rejected Carnaval’s argument that Berman had waived its demand for arson-specific instructions and that Berman bore the risk of loss from non-arson-induced fires. It also held that Carnaval incorrectly applied the negative-implication canon, wherein the express mention of one thing implies the exclusion of another, stating not every positive statement of rights or obligations carries a negative implication. Further, the risk of loss provision’s clause including “perils beyond contractor’s reasonable control” amounted to a catch-all, to which the negative-implication canon cannot be applied. When read in totality, the provision clearly places risk of loss on Carnaval for perils such as arson. Berman was therefore entitled to have the jury decide whether the loss was caused by arson or another peril beyond its control.

Final judgment in favor of Carnaval was reversed, as was the trial court’s order denying Berman’s motion for attorneys fees, and the matter was remanded for a new trial.

Firm Highlights

Thought Leadership

Appellate Division Affirms Dismissal of Legal Malpractice Counterclaim Against Martin Law Firm

In Martin v. Loury, 2026 N.J. Super. Unpub. LEXIS 1617 (App. Div. July 15, 2026), Martin Law Firm represented Kirk Loury in an employment matter Mr. Loury filed against his former employer, Concord Equity Group Advisors LLC (“Concord”). The allegations included, among other things, that Loury was not fairly compensated for his employment with Concord. After a bench trial finding in Loury’s favor, the Appellate Division remanded this matter in February 2016 for a second trial. During the second trial, Concord CEO, Lee Argush, testified to lower compensation estimate than first trial. On remand, the second trial judge awarded Mr. Loury the same damages as the first judge, finding Mr. Argush not credible. After the findings during the second trial, Martin Law Firm filed an action against Mr. Loury to recover legal fees and costs of representing Mr. Loury in a second bench trial and Mr. Loury filed a counterclaim against Martin Law Firm for legal malpractice, alleging he should have received an even higher award in the second bench trial. In this allegation, Mr. Loury, through his expert, claimed that Martin Law Firm should have recalled Mr. Loury to the stand to rebut Mr. Argush’s testimony to allege an alternative theory of damages. Mr. Loury’s expert admitted that the second judge already rejected Mr. Argush's theory and accepted Loury's damages theory. The trial court barred Mr. Loury’s expert and dismissed Loury's counterclaim with prejudice before convening the collection trial, and the jury ruled in Martin Law Firm’s favor. Mr. Loury appealed the trial court's pretrial rulings barring his liability expert from testifying in support of his legal malpractice counterclaim, denying his motion for summary judgment on that counterclaim, and denying his motion to amend his counterclaim by adding attorney Joseph A. Martin as a codefendant. In affirming the trial court’s decision, the Appellate Division held that the trial court properly excluded Loury’s expert testimony in the counterclaim against Martin Law Firm because the expert could not explain how calling Loury as a rebuttal witness would have increased damages when the second judge already rejected Mr. Argush's testimony and accepted Loury's damages theory, making the expert’s causation opinion speculative. The Appellate Division also held that the trial court properly denied Mr. Loury's summary judgment motion on his malpractice counterclaim because reasonable minds could differ on whether Mr. Martin's alleged failures would have changed the second judge's damages award, given the judge already found Mr. Argush not credible, creating genuine factual disputes precluding summary judgment. Also, the Appellate Division held that the trial court properly denied Loury's May 2023 motion to add Joseph Martin individually because the statute of limitations expired in February 2022, six years after the 2016 appellate remand when Mr. Loury incurred new legal costs, and relation back did not apply because Mr. Loury knew Mr. Martin's identity throughout and strategically chose to sue only Martin Law Firm in his 2019 counterclaim.